Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 19/11/2021
This decision will be taken under urgency procedures.
Reason for urgency:
Recent high tides and weather events over the last four/five weeks have caused the Pier Landing Stage to deteriorate at an unexpected rate; to such an extent that emergency intervention is required to prevent further deterioration to the structure.
As the works are required in a very short time scale, next available low tides in early December 2021, we do not have the opportunity to tender a contract in line with the Joint Council's Contract Standing Orders and therefore wish to proceed under Clause 8.3.3. Emergency Works to allow direct award of a contract to JT Mackley Co Ltd to undertake all the necessary emergency and preventative works to the Pier and Land stage sub-structures.
Decision due: 19 Dec 2021 by Director for Place
Lead member: Worthing Cabinet Member for Regeneration
Lead director: Director for Place
Contact: Martin Randall, Director for Place Email: martin.randall@adur-worthing.gov.uk.
Consultation process
Legal, Finance and Procurement Team and Executive Member for Regeneration (WBC)