Issue details

DforDS&R/011/21-22 Window Replacement & Balcony Repairs to Portland House

Replacement of existing windows and external doors, replacement soffits and repairs to balcony balustrades and associated making good.

Decision type: Key

Reason Key: Capital Schemes, within the Capital Programme >£250,000;

Decision status: Recommendations Approved

Notice of proposed decision first published: 14/09/2021

Decision due: Not before 13th Oct 2021 by Director for Sustainability & Resources

Lead director: Paul Brewer

Contact: Kevin Smith, Principal Building Surveyor - Facilities & Technical Services Email: kevin.smith@adur-worthing.gov.uk.

Consultation process

Members were consulted on 9th September 2021 with regards to the window and door replacements. The balcony repairs are a health and safety issue which will be best managed by sharing the access scaffold for the window replacement project.

Decisions