DforE/002/20-21 Gas Supply Renewal Contract

Decision type: Key

Decision status: Recommendations Approved

Wards affected: (All Wards);

Notice of proposed decision first published: 29/07/2020

This decision will be taken under urgency procedures.

Reason for urgency:
To enable the Council to take advantage of the most competitive bid during the window of opportunity that the procurement process will provide. If we don’t, we run the risk of our tariffs increasing and being out of contract.

Decision due: Not before 29th Jul 2020 by Director for Place

Lead director: Martin Randall

Consultation process

Executive Members for Resources  and internal consultations with Strategic Sustainability Manager, Accountancy team and LASER Energy Buying Manager.