Decision Maker: Adur Cabinet Member for the Environment and Leisure, Worthing Cabinet Member for Communities, Culture and Leisure
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
This report was circulated to Councillors, and published on the Council’s website on 16 July 2024. The following consultation responses were noted by the decision maker:
Extensive internal and external consultation has taken place with partners, including
? HOPs consulting structural engineers (on behalf of Adur & Worthing)
? Hemiko Limited as part of the Heat Network
? Price & Myers structural consultants (on behalf of Hemiko)
? Adur & Worthing Surveyors and Facilities Team
? Adur & Worthing Operations & Sustainability Team
? Adur & Worthing Procurement & Legal Services Team
? Makers Construction
? MacConvilles (Quantity Surveyors & Cost Consultants)
No other responses were received.
Worthing Cabinet Member for Regeneration: I have reviewed the proposals and agree to approve the award of a contract to Makers Construction to the value of £483,598+vat.
Adur Cabinet Member for Environment and Leisure: I abstain from this decision as it is predominantly a Worthing matter.
The necessary repairs are critical for the planned plant installations scheduled for autumn 2024 and vital for maintaining the structural integrity of the car park. The car park plays an important role in our local economy and its revenue.
Not to carry out works would prevent commencement of the Heat Network project and have a detrimental effect on the integrity of the car park.
Publication date: 25/07/2024
Date of decision: 25/07/2024
Effective from: 02/08/2024