Buckingham Multi-Storey Car Park Regeneration Scheme

DECISIONS CAN BE IMPLEMENTED AT 5PM ON THE DAY THAT A CALL-IN EXPIRES. DECISIONS MAY BE ENACTED AFTER 5PM ON THE DAY PRIOR TO THE DATE INDICATED BELOW IN THE 'EFFECTIVE FROM' COLUMN

Decision Maker: Joint Strategic Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

Before the Committee was a report by the Director for the Economy, copies of which had been circulated to all Members and a copy of which is attached to the signed copy of these minutes as Item 16. 

 

The report requested that Members agree to the recommended virement to enable the re-profiling of the programme of works for Buckingham and High Street Multi-Storey Car Park refurbishment projects, allowing capital funds of £800,000 to be brought forward for use into the 2020/21 budget year.  

 

The recommendations in the report were proposed by Councillor Kevin Jenkins, seconded by Councillor Daniel Humphreys and unanimously agreed by the Committee.  

 

Decision:  

 

The Joint Strategic Committee agreed a budget virement of £800,000 from the capital allocation for High Street MSCP to the Buckingham MSCP project budget.  This would enable the regenerative benefits and improvement options identified, to be incorporated into the Buckingham MSCP scheme. 

 

Call In: 

 

The call-in deadline for this decision will be 5.00pm on 19 June 2020.

 

Report author: Assistant Director Regenerative Development (CLT)

Publication date: 12/06/2020

Date of decision: 09/06/2020

Decided at meeting: 09/06/2020 - Joint Strategic Committee

Effective from: 20/06/2020