Joint 3rd Quarter Capital Investment Programme & Projects Monitoring 2024/25

DECISIONS CAN BE IMPLEMENTED AT 5PM ON THE DAY THAT A CALL-IN EXPIRES. DECISIONS MAY BE ENACTED AFTER 5PM ON THE DAY PRIOR TO THE DATE INDICATED BELOW IN THE 'EFFECTIVE FROM' COLUMN

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: No

Is subject to call in?: Yes

Decisions:

Before the Committee was a report by the Director for Sustainability and Resources, copies of which had been circulated to all Members and a copy of which is attached to the signed copy of these minutes as Item 7.

 

The report updated the Committee on the progress made on the delivery of the 2024/25 Capital Investment Programme for Adur District Council and Worthing Borough Council. The programme included schemes which supported the delivery of services by the Joint Services Committee.

 

 

 

Decision:

 

1)    That the reprofiling of the Adur District Council capital schemes as advised in paragraph 7.1.2 and appendix 2 be noted.

 

2)    That the reprofiling of the Worthing Borough Council capital schemes as advised in paragraph 7.2.1 and appendix 2 be noted.

 

3)    That the application of UKSPF funding and creation of a capital budget for Pier Decking Works in the 2024/25 programme as detailed in 6.3.1 be approved.

 

4)    That the virement of £5k underspend from the Roof Replacement project to the Splashpoint fire dampers replacement project as requested in 5.2.1 be approved

 

Call In: The call-in deadline for decisions will be 5.00pm on 18 March 2025

Publication date: 11/03/2025

Date of decision: 06/03/2025

Decided at meeting: 06/03/2025 - Joint Strategic Committee

Date comes into force if not called in: 19/03/2025

Call-in deadline date: 18/03/2025

Current call-in Count: 0