Decision details

Use of s106 contributions to improve Widewater Bridge, Lancing

DECISIONS CAN BE IMPLEMENTED AT 5PM ON THE DAY THAT A CALL-IN EXPIRES. DECISIONS MAY BE ENACTED AFTER 5PM ON THE DAY PRIOR TO THE DATE INDICATED BELOW IN THE 'EFFECTIVE FROM' COLUMN

Decision Maker: Joint Strategic Committee

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decisions:

Before the Committee was a report by the Director for the Economy, copies of which had been circulated to all Members and a copy of which is attached to the signed copy of these minutes as Item 11. 

 

The report sought authority to release s106 funds to deliver an improvement scheme for the Widewater bridge in Lancing.

 

The majority of funds were held by the County Council but the scheme required £103,773 held by Adur District to fully fund the scheme.  Whilst, these funds were specifically held for transport improvement schemes as the total exceeds £100,000 Committee approval to release the funds was required.  

 

The report set out some of the approval processes already undertaken by the County Council and described some of the key improvements to be undertaken to improve accessibility to the seafront cyclepath.         

 

The recommendations in the report were proposed by Councillor David Simmons, seconded by Councillor Neil Parkin and unanimously agreed by the Committee.

 

Decision:  

 

The Joint Strategic Committee agreed to release £103,773 towards the proposed improvement scheme to Widewater Bridge and agreed that the scheme be added to the capital programme.

 

Call In: 

 

The call-in deadline for this decision will be 5.00pm on 19 June 2020.

 

Report author: James Appleton

Publication date: 12/06/2020

Date of decision: 09/06/2020

Decided at meeting: 09/06/2020 - Joint Strategic Committee

Effective from: 20/06/2020

Accompanying Documents: